Managed Pressure Drilling - Operational Considerations

MPD Planning
Planning meetings should provide information about:
  • Casing design
  • Mud program
  • Hydraulics analyses
  • Well plan
  • Pressure profiles through the applicable hole sections
  • Rig equipment specifications and layout
  • Rig / well data acquisition and communication
  • Drilling tools specifications
  • MPD system and RCD specifications and functionality
  • HSE case reviews
  • HAZID / HAZOP
  • Preliminary operational procedures
  • Crew training
  • Rig-site & operational support
  • Regulatory issues
  • Rig site objectives, schedule, results, and actions

Value proposition - quantify the value that MPD will deliver relative to strong economic drivers

  • Drill time and/or cost savings
  • Increased access to reserves in depleted reservoirs or smaller reservoirs that may be uneconomic for conventional drilling
  • The number of wells that cannot be drilled conventionally but can be with MPD
  • Improved safety

MPD equipment and rig compatibility

  • Identify the optimum location on the rig for the MPD equipment keeping in mind its safety specifications and deck load ratings of offshore rigs
  • Quantify the amount and size of the piping that will be needed to interconnect the MPD and rig equipment, the pressure drop in the piping, the number of “elbow” connections, and its pressure rating
  • Identify the modifications that will have to be made to the rig equipment to connect the MPD
  • Ensure sufficient space is available between the top of the BOP stack and the rig floor for installation of the RCD

Drilling hydraulics - an essential part of drilling and well design but critical for MPD applications

  • Drilling pressure window must be defined based on the pore pressure / fracture gradient (PP/FG) plot
  • Establish the minimum BHPs for well control and borehole stability and the maximum BHP for lost circulation
  • Model the casing and drill pipe geometries with the planned mud properties at optimum drilling parameters
  • Define the EMW of the AFP while circulating at planned drilling rates
  • Evaluate alternate mud weight scenarios with MPD to reduce static mud weight and ECD at the modeled flow rates, rotary speed and penetration rate
  • Define the pressure reference or set point to be held while drilling and during connections
  • Define the tolerance window around the setpoint pressure that establishes the minimum and maximum allowable fluctuations

Personnel Training

  • Plan and conduct Hazard Identification (HAZID) and Hazard Operability (HAZOP) workshops to review the MPD system and define the potential risks
  • Identify the corresponding mitigation or response actions for each risk element
  • Categorize the HAZID results into drilling, connection, and tripping events and their relative risk (e.g., under-pressure or over-pressure)
  • Conduct training in at least two stages - classroom and on-site - to prepare the rig and service crews
  • In the classroom introduce MPD concepts, define the value and case for action, provide details of the MPD system components, and review the contingency plans defined in the HAZOP workshops
  • At the well site provide pre-tour presentations and walk through equipment installation and operation
  • It is highly recommended to test the MPD system functionality and practice contingency plan actions during the trip prior to drilling the shoe

Procedures - develop procedures for every major phase of the particular MPD operations which should include the following:

  • Testing and commissioning of the primary pressure control system after arrival at the point of embarkation and prior to shipment to the well
  • Placement, rig up, piping layout and connection,  and power connection,
  • Formal wellsite testing and commissioning involving specific operating scenarios and contingencies
  • Making the transition from pumps-on while drilling to pumps-off to make a connection and back
  • Describe the method for tripping out of the well before reaching TD
  • Any task that will affect the pressure regime of the well such as:
Picking up off bottom
Reducing the pump stroke rate
Stopping the mud pumps suddenly
Trips in and out of the hole
Plugged drill string or nozzles
Mud pump washout
Change in mud properties
Increasing ROP (induces more cuttings in the annulus)